Net Metering Application Process in the Philippines 2026
Net Metering Application Process in the Philippines
Begin with the distribution utility serving your electricity account. Net metering is a regulated interconnection and billing arrangement; installing equipment does not by itself approve export.
Step 1: Confirm eligibility and system size
Meralco's net-metering program has a ceiling of not more than 100 kW, subject to technical approval. Larger qualifying projects may use a separate DER pathway. Confirm how the utility assesses your proposed array and inverter capacities before ordering.
Step 2: Define engineering and application responsibilities
Have a qualified provider assess the roof, electrical service, consumption and proposed equipment. Ask who will prepare the professional design documents, secure permits and coordinate commissioning.
You may handle customer submissions yourself or use an authorised representative. Meralco's process expressly provides for representative documentation; a homeowner is not automatically prohibited from applying personally. Professional design and installation requirements still apply.
Step 3: Submit current forms
Obtain the latest checklist. For Meralco, the form covers the account, applicant, project, provider, equipment and relevant declarations. Representative documents and an annex for multiple equipment models or primary-metered applications may apply.
Use the actual checklist rather than an assumed list of four documents. Retain proof of submission and the application reference. Meralco application guide
Step 4: Complete technical evaluation
Meralco performs the Distribution Impact Study and identifies any further assessment, Distribution Asset Study or network work. Hosting capacity depends on existing conditions and other connected generation.
Published transformer figures are indicative aggregate references, not guaranteed capacity for each customer. The earlier table assigning fixed per-connection capacities was removed.
Step 5: Coordinate inspection and permits
Arrange the service-entrance inspection, resolve corrections, and obtain applicable LGU permits and CFEI documentation. Confirm the current accepted process where a deemed-approval provision is claimed; keep the required evidence.
DOE's April 2026 announcement describes emergency processing periods and their duration conditions. These should not be confused with a guaranteed equipment-installation-to-billing schedule.
Step 6: Complete agreements and assessed payments
Meralco's published stages include the Net Metering Agreement, Fixed-Asset Boundary Document, remaining documents and assessed payments. If declining the optional REC meter, follow the prescribed affidavit and waiver process.
Meralco says submission, the DIS, testing and commissioning are not charged to the applicant. Other costs can apply. Ask for an itemised assessment; do not confuse a Difference in Meter Cost with a DIS charge. The earlier “Distribution Impact Methodology Certificate” fee description was unsupported.
Step 7: Metering, commissioning and ERC transmittal
Meralco installs or configures approved meters and conducts grid-safety checks. Its published process then includes transmittal of completed documents and payment records to the ERC for Certificate of Compliance processing.
Follow the utility's actual sequence rather than assuming a pre-issued COC is always required before every preceding step. Confirm the start of net-metering service and check subsequent bills.
While the application is pending
Do not assume zero-export settings alone authorise operation. Ask which own-use or net-metering requirements apply. Unapproved exports may create safety and metering problems; the behaviour of an old meter must not be assumed.
Corrected 16 November 2026: removed invented fee labels, unsupported fee caps, a mandatory-installer submission claim, fixed transformer allocations and blanket operating advice.