ERC Updates on Net Metering Rules and Interconnection Standards in PH

ERC Updates on Net Metering Rules and Interconnection Standards in PH

ERC Net-Metering Updates and Interconnection Standards in the Philippines

Net-metering rules govern participation and billing. Interconnection requirements govern how the generating system connects safely. Both must be addressed before a customer relies on export credits.

What the 2025 amendments changed

ERC Resolution No. 15, Series of 2025, issued on 27 August 2025, includes banking and rollover of credits, conditional transfer when property ownership changes, published utility program information and voluntary REC metering.

The ERC announcement calls for quarterly transformer hosting-capacity disclosures. These figures inform planning but do not replace a project-specific technical assessment.

The capacity distinction

Meralco's current guidance states a net-metering ceiling of not more than 100 kW. Larger qualifying projects may use a separate DER route. Net metering and DER should not be treated as interchangeable programs.

Billing is based on peso credits

The export rate differs from the full retail import rate. Eligible exports earn a credit using the applicable monthly blended generation cost. Use the actual utility billing method rather than subtracting exported kWh directly from imported kWh.

Some bill components depend on consumption while others follow separate rules; describing all distribution, transmission and metering charges as fixed is inaccurate. Ask the utility to explain your particular bill.

What technical review examines

Meralco's Distribution Impact Study considers capacity, transformer loading, voltage, power quality, protection and available hosting capacity. Its application guide identifies this as part of the evaluation, not simply a requirement above an unspecified larger-system threshold.

Further measurement, a Distribution Asset Study, corrections or network work may be identified. A certified inverter is one part of the proposal, not a guarantee of approval.

Safety requirements need a complete design

The installation must not energise utility lines during an outage. Inverter settings, isolation, transfer equipment, disconnects, grounding and wiring must be specified by the responsible professionals and meet the applicable utility requirements.

Avoid installing hardware based on a generic online checklist alone. A system may provide backup to approved isolated home circuits while still stopping supply to utility lines; do not confuse those two functions.

Follow the current application stages

Meralco publishes application, evaluation, inspection, completion, commissioning and ERC-transmittal stages. Confirm local permits and accepted inspection documentation, then complete agreements and assessed payments.

DOE's April 2026 emergency fast-track announcement specifies shortened processing periods and duration conditions. Distinguish an applicable administrative deadline from equipment procurement, physical works and the first credited bill.

Keep evidence and check changes

Retain submitted forms, acknowledgments, approvals, equipment data, commissioning records and settings. If a delay occurs, request the pending item and required action in writing. Contact the utility before materially altering the approved system.

Reviewed 16 November 2026: clarified DIS scope, program boundaries, tariff terminology and the distinction between grid isolation and home backup.