Net Metering: Your Rooftop's Power Rules

Net Metering: Your Rooftop's Power Rules

Rooftop Solar Net Metering: The Rules Homeowners Should Understand

Net metering lets an eligible customer export surplus renewable electricity through an approved connection and receive bill credits. A safe installation, approved metering and the utility's billing rules all matter.

Capacity is only one eligibility check

Meralco states a ceiling of not more than 100 kW for net metering. The electricity account, equipment, technical design, service arrangement and local network conditions must also qualify. Do not assume a roof suitable for panels guarantees grid approval.

Export credits are not full retail compensation

The earlier version of this article incorrectly described a one-for-one retail-rate credit. Meralco explains that eligible exported kWh receive a peso credit based on the applicable monthly blended generation cost.

Imports and exports are measured separately. Total generation and total household consumption are different quantities from the meter's export and import readings.

Use current documents and assessments

Meralco's application guide includes customer and equipment information, representative documents where applicable, technical review, inspection, local permits, agreements and payments. A summary of four documents cannot cover every case.

Do not rely on the earlier article's universal ₱3,000 meter-cost cap. Meralco identifies an applicable meter-cost difference among possible assessed charges. Submission, the DIS, testing and commissioning are not charged to the applicant, while other project costs may apply.

REC metering is a separate choice

A REC meter measures gross generation and is voluntary under the amended rules. If declining it, follow the applicable affidavit, waiver and estimation procedure. This does not remove the need for approved import/export billing metering.

Credits and ownership changes

Unused credits can be banked for future bills under the applicable account and agreement conditions. They are bill credits, not automatically a cash payment. A property-ownership transfer can be allowed subject to conditions such as the original owner's conforme letter. ERC announcement

Operate and expand safely

The design must prevent backfeeding utility lines during outages. Backup for home loads requires the appropriate equipment and approved isolation arrangement; a standard grid-connected system should not be assumed to provide it.

Ask the utility before changing array or inverter capacity, batteries, protection, transfer equipment or operating mode. Changes may require renewed technical review and commissioning.

Assess the investment

Review current rates, direct daytime use, expected exports and realistic production. Consider maintenance, financing and replacements. Net metering does not guarantee a zero bill, a fixed savings percentage or positive cash flow.

Keep a handover file containing designs, permits, inspection and commissioning records, equipment details, warranties and monitoring access. Use it when checking bills or seeking after-sales service.

Corrected 16 November 2026: removed false full-retail export compensation and unsupported universal fee, document and timeline claims.