Who is Eligible for Net Metering in the Philippines? A Clear Guide

Who is Eligible for Net Metering in the Philippines? A Clear Guide

Who Is Eligible for Net Metering in the Philippines?

Net metering is for qualified electricity end-users with eligible on-site renewable-energy systems connected under the applicable distribution utility process. Eligibility depends on more than owning solar panels.

Check the capacity ceiling

Meralco states a ceiling of not more than 100 kW, subject to approval. The previous version of this article incorrectly said that the ERC raised the limit to 1 MW in 2022.

Meralco describes a separate distributed-energy-resource pathway for certain systems above 100 kW up to 1 MW. That pathway has different requirements and should not be presented as net metering.

Residential, business and institutional customers

Meralco's guidance says qualified new and existing customers may apply, including residential, business, industrial and government customers. The account, system, service arrangement, technical design and network conditions must qualify.

A customer category alone does not guarantee approval. For a rented property, condominium or shared roof, establish the necessary property rights and authorisations before designing the installation. Ask the utility which account and representative documents apply.

Customers outside Meralco's franchise area should obtain their own utility's current net-metering checklist and technical requirements.

Eligible renewable technologies

Solar PV is common, but Meralco also identifies wind, hydro, biomass and other permitted renewable technologies. Each proposal remains subject to technical and interconnection review.

The equipment, protection and operating arrangement must suit the project. A renewable label or manufacturer certificate is not sufficient by itself.

Network and installation suitability

The utility assesses whether the proposed connection can be accommodated safely. For Meralco, the application process includes a Distribution Impact Study, inspection and any required corrections. Published hosting capacity is an indicative planning reference; actual conditions can limit approval.

The property also needs a suitable installation design, including roof and electrical assessment where applicable. Do not infer structural suitability from available roof area alone.

Documents and professional responsibility

Start with the current utility forms and LGU requirements. Identify the account holder, authorised representative if any, equipment and responsible provider. Arrange the professional design documents and inspection records required for the project.

Have the contract specify responsibility for permits, utility submissions, corrections, fees and commissioning. Meralco's process includes transmittal to the ERC for Certificate of Compliance processing; follow the actual current sequence.

Financial expectations

Eligible exports receive bill credits rather than a one-for-one retail-rate exchange. Self-consumption, export rates, installation costs and remaining bill charges determine the benefit.

Eligibility does not guarantee a payback period, a particular system price or a zero bill. Use current quotations and a site-specific production and demand model.

Before proceeding

Ask the utility to confirm the applicable pathway, proposed capacity and account requirements. Keep approvals and commissioned settings, and consult the utility before material expansion or modification.

Corrected 16 November 2026: removed the false capacity expansion, automatic sector eligibility and unsupported standard costs and payback figures.