Meralco Net Metering: 5 Setup Tips
Meralco Net Metering: Five Setup Tips Before You Apply
Preparation helps prevent avoidable corrections. Use Meralco's current forms and define the installer's responsibilities before work begins.
1. Check the property and service entrance
Ask the provider to assess roof suitability and the electrical service before finalising the design. Record any required repairs or modifications, their cost and who will perform them. Avoid using generic meter-height or wire-size figures from an article as installation instructions.
Meralco's application process includes service-entrance inspection and correction of identified issues. The utility's review does not replace the installer's design responsibility.
2. Coordinate local permits early
Get the applicable electrical-permit and Certificate of Final Electrical Inspection requirements from the Office of the Building Official. Confirm the current procedure for your property and any claimed deemed-approval route rather than assuming an elapsed deadline authorises energisation.
Keep application acknowledgments, receipts, inspection records and approved documents. If existing work lacks records, ask the authority what is needed; penalties and regularisation steps should not be guessed.
3. Model direct use and export separately
Match the proposal to your electricity demand and realistic solar production. Meralco's billing guidance explains that exported kWh earn peso credits using the applicable monthly export rate. They do not offset imported kWh one-for-one at the full retail rate.
Request a calculation using current rates, declared assumptions and alternative system sizes. There is no universal “two exported kWh equal one imported kWh” ratio.
4. Ask for a written cost breakdown
Separate installer services from official payments. Meralco states that submission, the Distribution Impact Study, testing and commissioning are not charged to applicants. Other charges may include permits, corrections, the ERC application fee, a meter-cost difference or case-specific study and network work.
Do not assume every net-metering customer must top up a bill deposit. If any deposit adjustment is requested, obtain the account-specific assessment and basis from Meralco.
5. Track each stage and confirm the operating arrangement
Keep the application reference, submissions and written status updates. Ask which item is pending and who must act. Physical installation, technical approval and the first credited bill are different milestones.
DOE announced an emergency fast-track directive in April 2026; confirm its current applicability. Meralco also explains that the full journey depends on documents, inspections, corrections, network conditions and commissioning.
Do not assume selecting zero-export mode alone makes a pending installation authorised. Ask Meralco which net-metering or own-use pathway applies. Never disable isolation or anti-islanding protection, and obtain confirmation before unapproved parallel operation or export.
Corrected 16 November 2026: removed unsupported standard fees, compulsory deposit examples, blanket timelines and blanket authorisation of zero-export operation.